In Energy

Coleman Station Wet FGD Upgrade

MARKET

Energy

OWNER

Big Rivers Electric

CLIENT

Casey Industrial

LOCATION

Hawesville, KY

This was an environmental compliance project for Big Rivers Electric. It was awarded to an EPC firm which needed a highly skilled welding company to perform the erection of the alloy absorber vessel.

The scope included fabrication and erection of Siemens Environmental WFGD system, including all alloy fit up and welding. GrayWolf also provided the supply of the vessel.

Multiple cranes were required for our execution making coordination with the General Contractor key as they needed a large footprint for access. The project was delivered on budget and on schedule.

Quote: Integer auctor magna mi, non laoreet mi tristique sed. Nam tincidunt dui eleifend ecitur egestas. Pellentesque semper non erat et.

John Doe

-Western Australian Department of Treasury

Key Project Contacts

FIRSTNAME LASTNAME

Business Development

linkedin-blue

FIRSTNAME LASTNAME

Project Manager

linkedin-blue

FIRSTNAME LASTNAME

GM

linkedin-blue
Contact Us

We're not around right now. But you can send us an email and we'll get back to you, asap.

Coal Combustion Residual ProjectMill Creek AQC Units 1-4 Upgrade