In Oil & Gas

Gorgon Downstream LNG

Leveraging the DBM Global platform of companies, GrayWolf is enabled to provide a complete end-to-end solution from design through to fabrication, construction and facility services. Learn more about how we can de-risk your next project.

MARKET

Oil & Gas

CLIENT

Civmec Construction & Engineering

LOCATION

Barrow Island, Australia

The Downstream Project is part of the Gorgon Project, developing the Gorgon and Jansz-Io gas fields. It involves the liquefied natural gas plant, condensate handling facilities, carbon dioxide injection facilities and other support facilities. It also includes 3 trains each capable of producing 5 million tons of liquefied natural gas per year; a considerable portion of the overall 15.6 million ton per annum liquefied natural gas (LNG) plant on Barrow Island.

The scope included the structural connection design, modeling and structural detailing of 11,400 tons of stick build steel for all of the support structures and the 3 process trains on the Downstream Gorgon LNG Project. Initially it was for standard connect design with an allowance of 15% for non-standard connections, however, after final structural design drawings were provided, a total of 2,300 non-standard connections designs were required needing additional resources. Structural design of the building was performed in the UK yet steel connection design was required to comply with Australian Codes. The non-standard connections were often heavily loaded with loads requiring in-depth analysis.

The average time for non-standard connection design was reduced by 75% over the life of the project. Interfacing of the PDMS, structural and construction models were required throughout the project and required regular communication with the head client Kellogg Joint Venture on schedule priorities.

Some of the major areas carried out in structural engineering and detailing included:

  • Amine absorbers and regenerator units
  • MEG injection pump area piperacks
  • Cryogenic heat exchangers
  • HP fuel gas mixing units
  • Oily water treatment and firewater units
  • Waste heat recover units
  • Condensate stabilization & storage buildings
  • Pipe racks, pipe supports and calve access platforms
  • Power generation units
  • Jetty head / loading berth including load out lines

John Doe

-Western Australian Department of Treasury

Key Contacts

JOE MILLER

Business Development

linkedin-blue

CHRIS MOSHELL

Project Manager

linkedin-blue

STEVEN HAYES

GM

linkedin-blue

MARKET

Oil & Gas

OWNER

Chevron

CLIENT

Civmec Construction & Engineering

LOCATION

Barrow Island, Australia

The Downstream Project is part of the Gorgon Project, developing the Gorgon and Jansz-Io gas fields. It involves the liquefied natural gas plant, condensate handling facilities, carbon dioxide injection facilities and other support facilities. It also includes 3 trains each capable of producing 5 million tons of liquefied natural gas per year; a considerable portion of the overall 15.6 million ton per annum liquefied natural gas (LNG) plant on Barrow Island.

The scope included the structural connection design, modeling and structural detailing of 11,400 tons of stick build steel for all of the support structures and the 3 process trains on the Downstream Gorgon LNG Project. Initially it was for standard connect design with an allowance of 15% for non-standard connections, however, after final structural design drawings were provided, a total of 2,300 non-standard connections designs were required needing additional resources. Structural design of the building was performed in the UK yet steel connection design was required to comply with Australian Codes. The non-standard connections were often heavily loaded with loads requiring in-depth analysis.

The average time for non-standard connection design was reduced by 75% over the life of the project. Interfacing of the PDMS, structural and construction models were required throughout the project and required regular communication with the head client Kellogg Joint Venture on schedule priorities.

Some of the major areas carried out in structural engineering and detailing included:

  • Amine absorbers and regenerator units
  • MEG injection pump area piperacks
  • Cryogenic heat exchangers
  • HP fuel gas mixing units
  • Oily water treatment and firewater units
  • Waste heat recover units
  • Condensate stabilization & storage buildings
  • Pipe racks, pipe supports and calve access platforms
  • Power generation units
  • Jetty head / loading berth including load out lines

Project capabilities provided through companies of DBM Global. Learn more about how we leverage both our construction and technology expertise held across our platform of companies to deliver a derisked end-to-end solution for your asset’s lifecycle.

Quote: Integer auctor magna mi, non laoreet mi tristique sed. Nam tincidunt dui eleifend ecitur egestas. Pellentesque semper non erat et.

John Doe

-Western Australian Department of Treasury

Key Project Contacts

FIRSTNAME LASTNAME

Business Development

linkedin-blue

FIRSTNAME LASTNAME

Project Manager

linkedin-blue

FIRSTNAME LASTNAME

GM

linkedin-blue

Let’s talk about
your next project


    Contact Us

    We're not around right now. But you can send us an email and we'll get back to you, asap.