HMPL Boiler Furnace Rebuild

MARKET

Energy

OWNER

Henderson Municipal Power & Light

CLIENT

Big Rivers Electric

LOCATION

Seabree, KY

To overcome the many obstacles in meeting the aggressive eight week outage schedule, GrayWolf developed an innovative way to approach a major water wall rebuild that had limited access by installing a Derrick crane onto one of the adjacent boilers during the pre-outage.

Our scope included replacing 75% of this 190 megawatt boiler water wall in fifty-two panels for a total of 2190 tube welds. GrayWolf was successful in obtaining a dry hydro-test after the chemical clean.

Quote: Integer auctor magna mi, non laoreet mi tristique sed. Nam tincidunt dui eleifend ecitur egestas. Pellentesque semper non erat et.

John Doe

-Western Australian Department of Treasury

Key Contacts

JOE MILLER

Business Development

linkedin-blue

CHRIS MOSHELL

Project Manager

linkedin-blue

STEVEN HAYES

GM

linkedin-blue

Let’s talk about
your next project


    Contact Us

    We're not around right now. But you can send us an email and we'll get back to you, asap.

    JEA Harp Replacement-GrayWolf Integrated Construction CompanyWilson Outage-GrayWolf Integrated Construction Company