HMPL Boiler Furnace Rebuild
MARKET
Energy
OWNER
Henderson Municipal Power & Light
CLIENT
Big Rivers Electric
LOCATION
Seabree, KY
To overcome the many obstacles in meeting the aggressive eight week outage schedule, GrayWolf developed an innovative way to approach a major water wall rebuild that had limited access by installing a Derrick crane onto one of the adjacent boilers during the pre-outage.
Our scope included replacing 75% of this 190 megawatt boiler water wall in fifty-two panels for a total of 2190 tube welds. GrayWolf was successful in obtaining a dry hydro-test after the chemical clean.
Quote: Integer auctor magna mi, non laoreet mi tristique sed. Nam tincidunt dui eleifend ecitur egestas. Pellentesque semper non erat et.
John Doe
-Western Australian Department of Treasury
Key Contacts
JOE MILLER
Business Development
CHRIS MOSHELL
Project Manager
STEVEN HAYES
GM