In Renewables

Fort Bend County Solar Farm

MARKET

Renewables

OWNER

ACCIONA

CLIENT

Wanzek

LOCATION

Fort Bend County, TX

Fort Bend County Solar Farm is the first solar PV plant in the state of Texas. It has an energy capacity of 240 MW PV.

GrayWolf’s scope of work included purchasing, fabricating, coating and delivering 44,000 steel solar array piers to the solar project in South Texas.

The project required GrayWolf’s project team to work collaboratively with the client, who had not yet completed final design. In addition, pier material availability had become a critical issue and was endangering the project schedule. GrayWolf was able to work with the client to help them through certain design considerations and then proactively source the material so production could begin on schedule. GrayWolf’s project and shop production teams worked daily with the client’s site team to effectively coordinate and manage the logistics required to move daily truckloads of materials from GrayWolf’s fabrication facilities, to the galvanizer, to the site. The project was completed on time and the client was able to meet their pier installation schedule per their contract with the project owner.

Quote: Integer auctor magna mi, non laoreet mi tristique sed. Nam tincidunt dui eleifend ecitur egestas. Pellentesque semper non erat et.

John Doe

-Western Australian Department of Treasury

Key Contacts

JOE MILLER

Business Development

linkedin-blue

CHRIS MOSHELL

Project Manager

linkedin-blue

STEVEN HAYES

GM

linkedin-blue
Contact Us

We're not around right now. But you can send us an email and we'll get back to you, asap.