In Energy

Absorber Modularization

MARKET

Energy

OWNER

Duke Energy

CLIENT

Babcock & Wilcox Company

LOCATION

North Bend, OH

GrayWolf was awarded a lump sum contract for the modularization of a 2205 alloy absorber with barge shipment to the North Bend, Ohio job site.

The absorber was built in seven (7) module sections with all internal supports and headers installed. GrayWolf successfully complied with the strenuous project, cleanliness requirements of the alloy material (iron contamination), as well as a very aggressive completion schedule.

Quote: Integer auctor magna mi, non laoreet mi tristique sed. Nam tincidunt dui eleifend ecitur egestas. Pellentesque semper non erat et.

John Doe

-Western Australian Department of Treasury

Key Project Contacts

Greg Leavitt

Business Development

linkedin-blue

Mark Stoller

Project Manager

linkedin-blue

STEVEN HAYES

GM

linkedin-blue
Contact Us

We're not around right now. But you can send us an email and we'll get back to you, asap.

TC2JEA Harp Replacement-GrayWolf Integrated Construction Company