In Pulp-Paper-Wood

7 Effect Black Liquor Evaporator Project

MARKET

Pulp, Paper & Wood

OWNER

Georgia Pacific

CLIENT

Andritz

The project included the installation of a five stage evaporator system with GrayWolf self-performing civil foundations, structural steel erection, equipment installation, installation of all associated piping, BOP mechanical and commissioning support for Andritz.

Project duration was 18 months with 300,000 man hours.