In Energy

HMPL Boiler Furnace Rebuild

MARKET

Energy

OWNER

Henderson Municipal Power & Light

CLIENT

Big Rivers Electric

LOCATION

Seabree, KY

To overcome the many obstacles in meeting the aggressive eight week outage schedule, GrayWolf developed an innovative way to approach a major water wall rebuild that had limited access by installing a Derrick crane onto one of the adjacent boilers during the pre-outage.

Our scope included replacing 75% of this 190 megawatt boiler water wall in fifty-two panels for a total of 2190 tube welds. GrayWolf was successful in obtaining a dry hydro-test after the chemical clean.

Quote: Integer auctor magna mi, non laoreet mi tristique sed. Nam tincidunt dui eleifend ecitur egestas. Pellentesque semper non erat et.

John Doe

-Western Australian Department of Treasury

Key Contacts

JOE MILLER

Business Development

linkedin-blue

CHRIS MOSHELL

Project Manager

linkedin-blue

STEVEN HAYES

GM

linkedin-blue
Contact Us

We're not around right now. But you can send us an email and we'll get back to you, asap.

JEA Harp Replacement-GrayWolf Integrated Construction CompanyWilson Outage-GrayWolf Integrated Construction Company