Fernandina Beach Mill
Fernandina Beach Mill

Papermill Evaporator System Upgrade

GrayWolf's scope of work included structural steel erection, installation of multi-stage evaporators, installation of all associated piping, self-performed turn-key construction for electrical, mechanical, insulation and commissioning support for AH Lundberg.

The project ran a duration of 8 months with 140,000 man hours.

MARKET
Pulp & Paper
OWNER
Westrock
CLIENT
Westrock – AH Lundberg OEM
LOCATION
Fernandina Beach, FL