Papermill Evaporator System Upgrade
GrayWolf's scope of work included structural steel erection, installation of multi-stage evaporators, installation of all associated piping, self-performed turn-key construction for electrical, mechanical, insulation and commissioning support for AH Lundberg.
The project ran a duration of 8 months with 140,000 man hours.