Evaporator Crystallizer Legacy Project
The Evaporator – Crystallizer Legacy project took place in 2014 for the duration of 7 months. GrayWolf's scope of work included the erection of (3) MEE Evaporators & (3) Salt Crystallizers.
Our teams worked with the client and owners to install and erect OEM equipment. We planned and implemented logistical, material handling, staging of materials with detail scope/task planning to maintain a safe and productive schedule within harsh climate conditions throughout the duration of this project.
We achieved 72,000 craft man-hours for the scope of work with zero recordable or lost time incidents.