Foley Mill
Foley Mill
Foley Mill
Foley Mill

7 Effect Black Liquor Evaporator Project

The project included the installation of a five stage evaporator system with GrayWolf self-performing civil foundations, structural steel erection, equipment installation, installation of all associated piping, BOP mechanical and commissioning support for Andritz.

Project duration was 18 months with 300,000 man hours.

MARKET
Pulp & Paper
OWNER
Georgia Pacific
CLIENT
Andritz