D.B. Wilson Generating Station Outage

GrayWolf staffed this aggressive outage at a D.B. Wilson Generating Station power plant replacing the super heat elements, air basket and seal change out, replacement and extensive repairs on the AQCS equipment and extensive ductwork repair.

The outage had a six week duration with a peak work force of 430 working a total of 161,000 man-hours.