Data Center Buildings 1 & 2

The scope of work for this project included the supply and installation of primary and secondary structural steel, joists, deck and miscellaneous steel. We adhered to a compressed schedule that required multiple (2-3) cranes working at the same time to expedite the accelerated timeline. The timetable necessitated that multiple fabrication facilities be involved in order to keep the cranes going.

There were also strict safety guidelines in place, primarily regarding man lifts and minimal walking of the steel.

These projects involved very precise BIM coordination (+/- ½"), which entailed us working closely with the contractor and design team to coordinate over 500 MEP floor penetrations and supports to be installed prior to the elevated floors being poured.
This LEED Gold-certified structure utilizes renewable energy within its campus.

MARKET
Data Center Ecosystem<
OWNER
Confidential
GENERAL CONTRACTOR
Holder Construction
TONNAGE
9,500
LOCATION
Social Circle, GA