Carbo Ceramics Capital Plant Expansion Phase II
Phase II of the expansion on this chemical processing plant began in 2014 and took 12 months to complete. GrayWolf's scope of work included foundation installation, structural steel erection, equipment installation, pipe installation, BOP pipe installation, and electrical/instrumentation services.
Our teams provided construction management and self-performed construction work for the client fulfilling the project's need for key planning and coordination. We achieved 185,000 craft man-hours during the scope of work including lost time incidents.